Administrative Approval Detail : शा0सं0 1543(1)/।।।(2)/21-40 (एम0एल0ए0) /2017टी0सी0 2 दिनांक 09.06.2021
TS Amount (lakhs) : 115.95 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
115.95
Resanction Cost :
115.95
Tentative Cost :
115.95
Exp. Upto Last Fy :
115.95
For CFY 2025-2026
Remaining :
0.00
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
115.95
Work completed
Sanction on : 4 years 3 weeks ago
09 Jun 2021
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 years 3 months ago
31 Mar 2023
Actual Completion Date : 2 years 6 months ago
31 Dec 2022
Physical Linear Components
Remark
पहाड़ कटान का कार्य पूर्ण। -- as on 08-Nov-2023