Work Profile Report [70W330]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई0 फाईल न0 25463 दि0 30.08.2022
TS Amount (lakhs) : 93.17 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
93.17
Resanction Cost :
93.17
Tentative Cost :
93.17
Exp. Upto Last Fy :
0.52
For CFY 2025-2026
Remaining :
92.65
Demand :
0.00
Allotment :
6.63
Exp in CFY :
0.00
Total Up to Date Exp :
0.52
Unstarted Work
Sanction on : 3 years 4 months ago
30 Aug 2022
Physical Progress:
At start of FY 2025-2026 :
15 %
Up to Date :
15 %
Tentative Completion date on : 1 year 2 months from now
31 Mar 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य की सैद्धान्तिक स्वीकृति भारत सरकार के पत्रांक FP/UK/ROAD/438638/2023, Dated 20-01-2026 द्वारा प्राप्त। एन0पी0वी0 भुगतान एंव कटान/छपान हेतु कार्यवाही गतिमान। -- as on 21-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: