Work Profile Report [70W331]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई0 फाईल न0 25463 दि0 30.08.2022
TS Amount (lakhs) : 20.08 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
20.08
Resanction Cost :
20.08
Tentative Cost :
20.08
Exp. Upto Last Fy :
9.23
For CFY 2024-2025
Remaining :
10.85
Demand :
3.00
Allotment :
5.21
Exp in CFY :
5.21
Total Up to Date Exp :
14.44
Construction Started
Sanction on : 2 years 2 months ago
30 Aug 2022
Physical Progress:
At start of FY 2024-2025 :
50 %
Up to Date :
50 %
Tentative Completion date on : 3 weeks 6 days ago
31 Oct 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पहाड़ कटान का कार्य प्रगति पर। -- as on 03-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: