Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 0.000 | 4 | 0.000 | 0.000 |
70W42 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 3867(0)/।।।(2)/17-40/(एमएलए) /2017 दि0 06.12.2017
TS Amount (lakhs) : 5.77 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
13.40
Resanction Cost :
13.40
Tentative Cost :
13.40
Exp. Upto Last Fy : 7.96
For CFY 2024-2025
Remaining : 5.44
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 7.96
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
6 years 7 months ago
06 Dec 2017
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
उपरोक्त मोटर मार्ग की सैद्धान्तिक स्वीकृति प्राप्त होने के उपरान्त विधिवत स्वीकृति हेतु हेतु अनुपालन आख्या इस कार्यालय के पत्रांक सं0 577/21सी0, दि0 24-02-2023 द्वारा प्रभागीय वनाधिकारी गढ़वाल वन प्रभाग पौड़ी को प्रेषित। उपरोक्त मोटर मार्ग की सैद्धान्तिक स्वीकृति प्राप्त होने के उपरान्त विधिवत स्वीकृति हेतु हेतु अनुपालन आख्या इस कार्यालय के पत्रांक सं0 577/21सी0, दि0 24-02-2023 द्वारा प्रभागीय वनाधिकारी गढ़वाल वन प्रभाग पौड़ी को आॅफलाइन प्रेषित। आॅनलाइन पोर्टल पर अनुपालना का विकल्प न खुलन के कारण परिवेश पोर्टल पर शिकायत सं0 पी0ए0आर0टी0आई0सी0-24009279 एंव 24009297, दि0 22.05.2024 के द्वारा आॅनलाइ्रन शिकायत दर्ज करायी गयी है। -- as on 27-May-2024
Physical Peramenters