Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.25 | 4.25 | 4.25 | 0 |
70W456 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई0 पत्रावली संख्या-48456, दिनांक 10.08.2023
TS Amount (lakhs) : 64.04 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
64.04
Resanction Cost :
64.04
Tentative Cost :
64.04
Exp. Upto Last Fy : 29.73
For CFY 2024-2025
Remaining : 34.31
Demand : 34.31
Allotment : 30.00
Exp in CFY : 0.00
Total Up to Date Exp : 29.73
Work completed
Physical Progress:
At start of FY 2024-2025 : 95 %
Up to Date : 100 %
Sanction on :
11 months 1 week ago
10 Aug 2023
Tentative Completion date:
1 month 1 week ago
05 Jun 2024
Actual Completion Date:
2 months 3 weeks ago
21 Apr 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का अन्तिमीकरण किया जा रहा है। -- as on 25-Jun-2024
Physical Peramenters