Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 30 | 30 | 0.000 | 30 | 0.000 | 0.000 |
70W462 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई-पत्रावली सं0-49198, दि0 25.08.2023।
TS Amount (lakhs) : 3.6 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
3.60
Resanction Cost :
3.60
Tentative Cost :
3.60
Exp. Upto Last Fy : 0.08
For CFY 2024-2025
Remaining : 3.52
Demand : 1.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.08
Survey work done
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 40 %
Sanction on :
10 months 3 weeks ago
25 Aug 2023
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध गठित। मृदा परीक्षण एवं स्थल चयन की कार्यवाही प्रस्तावित। -- as on 04-Jan-2024