Work Profile Report [70W477]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासन की ई0 पत्रावली सं0 50713, दि0 30.10.2023
TS Amount (lakhs) : 3.75 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
3.75
Resanction Cost :
3.75
Tentative Cost :
3.75
Exp. Upto Last Fy :
0.30
For CFY 2024-2025
Remaining :
3.45
Demand :
1.00
Allotment :
2.00
Exp in CFY :
1.68
Total Up to Date Exp :
1.98
Phase1 DPR Submitted
Sanction on : 1 year 3 weeks ago
30 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
60 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
संरेखण स्वीकृत। डी0पी0आर0 गठित कर अधी0अभि0 पौड़ी को प्रेषित। -- as on 01-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand