Work Profile Report [70W486]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : प्रमुख अभियन्ता एंव विभागाध्यक्ष, लो0नि0वि0, उत्तराखण्ड, देहरादून के पत्रांक 1588ध्01नियो0-2(एस0डी0आर0एफ0)ध्2023, दि0 30.12.2023।
TS Amount (lakhs) : 21.35 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
21.35
Resanction Cost :
21.35
Tentative Cost :
21.35
Exp. Upto Last Fy :
6.03
For CFY 2024-2025
Remaining :
15.32
Demand :
15.32
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
6.03
Work completed
Sanction on : 10 months 3 weeks ago
30 Dec 2023
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व अवशेष। -- as on 28-Mar-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: