Work Profile Report [70W513]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : शासन की ई0 पत्रावली संख्या-37773, दिनांक 08-02-2024
TS Amount (lakhs) : 222.2 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
222.20
Resanction Cost :
222.20
Tentative Cost :
222.20
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
222.20
Demand :
160.00
Allotment :
50.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 6 months 1 week ago
08 Feb 2024
Physical Progress:
At start of FY 2024-2025 :
2 %
Up to Date :
10 %
Tentative Completion date on : 6 months 4 weeks from now
14 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
दीवार निर्माण एवं सोलिंग का कार्य प्रगति पर। -- as on 26-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand