Work Profile Report [70W529]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासन की ई0 पत्रावली सं0 41863, दि0 15.03.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
236.18
Resanction Cost :
236.18
Tentative Cost :
236.18
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
236.18
Demand :
150.00
Allotment :
150.00
Exp in CFY :
50.26
Total Up to Date Exp :
50.26
Construction Started
Sanction on : 9 months 1 week ago
15 Mar 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
20 %
Tentative Completion date on : 4 months 2 weeks from now
15 May 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अतिरिक्त पहाड़ कटान, दीवार निर्माण का कार्य पूर्ण । सोलिंग का कार्य प्रगति पर। -- as on 21-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: