Work Profile Report [70W611]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शासन की ई0 पत्रावली सं0 37977, दि0 25-03-2025
TS Amount (lakhs) : 431.29 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
434.97
Resanction Cost :
434.97
Tentative Cost :
434.97
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
434.87
Demand :
344.55
Allotment :
300.00
Exp in CFY :
204.28
Total Up to Date Exp :
204.37
Construction Started
Sanction on : 7 months 4 weeks ago
25 Mar 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
75 %
Tentative Completion date on : 6 months 1 week from now
31 May 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी0-3 का कार्य पूर्ण। नाली निर्माण एंव क्रास ड्रेनेज कार्य प्रगति पर। -- as on 21-Nov-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: