Work Profile Report : 70W664
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शासन की ई0 पत्रावली सं0 37977/2022, दि0 05.08.2025
TS Amount (lakhs) : 256.27 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
256.27
Resanction Cost :
256.27
Tentative Cost :
256.27
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
256.27
Demand :
150.00
Allotment :
150.00
Exp in CFY :
45.76
Total Up to Date Exp :
45.76
Construction Started
Sanction on : 7 months 34 minutes ago
05 Aug 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
25 %
Tentative Completion date on : 5 months 6 days from now
12 Aug 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी0-1 का कार्य पूर्ण। जी0-2 का कार्य प्रगति पर। -- as on 02-Mar-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: