Work Profile Report [70W82]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 1541/।।।(2)/09-23(मु0मं0घो0)/09 दि0 31.03.2010
TS Amount (lakhs) : 86.11 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
105.00
Resanction Cost :
105.00
Tentative Cost :
105.00
Exp. Upto Last Fy :
71.30
For CFY 2025-2026
Remaining :
33.70
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
71.30
Work completed
Sanction on : 15 years 3 months ago
31 Mar 2010
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 months 6 days ago
30 Apr 2025
Actual Completion Date : 1 year 8 months ago
31 Oct 2023
Physical Linear Components
Remark
2 किमी0 में पहाड़ कटान पूर्ण। मुआवजा वितरण की कार्यवाही गतिमान। -- as on 09-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand