Work Profile Report [71W1010]
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष, लो0नि0वि0, उत्तराखण्ड, देहरादून के पत्रांक-191/14 याता (क)-उ0/2023 दि0 09/02/2024
TS Amount (lakhs) : 429.69 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
429.69
Resanction Cost :
429.69
Tentative Cost :
429.69
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
429.69
Demand :
429.69
Allotment :
38.28
Exp in CFY :
42.20
Total Up to Date Exp :
42.20
Construction Started
Sanction on : 9 months 2 weeks ago
09 Feb 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
20 %
Tentative Completion date on : 4 months 4 days from now
28 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
5.00 कि0मी0 में एस0डी0बी0सी0 कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 01-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand