Work Profile Report [71W1018]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष, लो0नि0वि0, उत्तराखण्ड, देहरादून के पत्रांक-388/14 याता (क)-उ0/2023 दि0 15/03/2024
TS Amount (lakhs) : 112.57 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
112.57
Resanction Cost :
112.57
Tentative Cost :
112.57
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
112.57
Demand :
112.57
Allotment :
60.16
Exp in CFY :
60.16
Total Up to Date Exp :
60.16
Construction Started
Sanction on : 8 months 1 week ago
15 Mar 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
78 %
Tentative Completion date on : 3 months 3 weeks from now
19 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 27-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand