Work Profile Report [71W1021]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष, लो0नि0वि0, उत्तराखण्ड, देहरादून के पत्रांक-388/14 याता (क)-उ0/2023 दि0 15/03/2024
TS Amount (lakhs) : 16.08 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
16.08
Resanction Cost :
16.08
Tentative Cost :
16.08
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
16.08
Demand :
16.08
Allotment :
11.87
Exp in CFY :
7.30
Total Up to Date Exp :
7.30
Construction Started
Sanction on : 8 months 1 week ago
15 Mar 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
50 %
Tentative Completion date on : 4 months 3 days from now
27 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 27-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: