Work Profile Report [71W1078]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शासन की ई0 पत्रावली 249698/2024/37977 दिनांक 24/10/2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
321.07
Resanction Cost :
321.07
Tentative Cost :
321.07
Exp. Upto Last Fy :
90.10
For CFY 2025-2026
Remaining :
230.97
Demand :
141.79
Allotment :
73.84
Exp in CFY :
61.58
Total Up to Date Exp :
151.68
Construction Started
Sanction on : 1 year 2 months ago
24 Oct 2024
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
35 %
Tentative Completion date on : 1 year 2 months from now
31 Mar 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Excess requirement 321.07 has been counted as tentative cost increased from to 321.07 .
मार्ग पर जी0 1, स्कपर, सुपर ऐलिवेशन, रिटेनिंगवाल, कैचपिट एवं क्रेश बैरियर का कार्य पूर्ण। वर्तमान में जी0 2 का कार्य प्रगति पर।
-- as on 14-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: