Work Profile Report [71W1100]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : श्शासन की ई0 पत्रावली 35543 दिनांक 11/03/2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
48.70
Resanction Cost :
48.70
Tentative Cost :
48.70
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
48.60
Demand :
48.60
Allotment :
30.00
Exp in CFY :
14.27
Total Up to Date Exp :
14.37
Construction Started
Sanction on : 4 months 4 weeks ago
11 Mar 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
30 %
Tentative Completion date on : 5 months 1 week from now
20 Jan 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Excess requirement 48.7 has been counted as tentative cost increased from to 48.70 .
कार्य प्रगति पर।
-- as on 04-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: