Work Profile Report [71W125]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-829/।।।-2/06 दि0 28/3/2006
TS Amount (lakhs) : 111.2 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
111.20
Resanction Cost :
277.11
Tentative Cost :
277.11
Exp. Upto Last Fy :
93.90
For CFY 2025-2026
Remaining :
183.21
Demand :
17.30
Allotment :
12.84
Exp in CFY :
1.18
Total Up to Date Exp :
95.08
Construction Started
Sanction on : 19 years 7 months ago
28 Mar 2006
Physical Progress:
At start of FY 2025-2026 :
60 %
Up to Date :
60 %
Tentative Completion date on : 1 year 10 months ago
31 Dec 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Excess requirement 165.91 has been counted as tentative cost increased from 111.2 to 277.11 . -- as on 30-Sep-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: