Work Profile Report [71W125]

fसमलख्ेात सम्पर्क मार्ग।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

Administrative Approval Detail : शा0सं0-829/।।।-2/06 दि0 28/3/2006

TS Amount (lakhs) : 111.2 Lacs

Budget Financial Head : SCSP ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

111.20

Resanction Cost :

111.20

Tentative Cost :

111.20

Exp. Upto Last Fy :

71.56

For CFY 2024-2025

Remaining :

39.64

Demand :

35.00

Allotment :

15.00

Exp in CFY :

2.10

Total Up to Date Exp :

73.66

Construction Started

Sanction on : 18 years 4 months ago

28 Mar 2006

Physical Progress:

At start of FY 2024-2025 :

60 %

Up to Date :

60 %

Tentative Completion date on : 7 months 2 weeks ago

31 Dec 2023

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
8
3
0.000
3
3.000
0.000

Remark

view all

ग्राम पटना के ग्रामवासियों द्वारा दीर्घकाल तक कार्य प्रारम्भ नहीं करने दिया गया। स्वीकृत लम्बाई 8 कि0मी0 के सापेक्ष 3 कि0मी0 लम्बाई में ही कार्य पूर्ण किया जाना सम्भव है। ग्रामवासियों द्वारा किये जा रहे विवाद को सुलझाने के उपरान्त 2.50 कि0मी0 लम्बाई में पहाड़ कटान का कार्य पूर्ण किया जा चुका है। शेष कार्य प्रगति पर। अवशेष लम्बाई 5 कि0मी0 लम्बाई का पुनरीक्षित आगणन गठित कर इस कार्यालय के पत्रांक-1702/5सी0 दिनांक 11/05/23 द्वारा रू0 160.16 लाख मात्र का अधीक्षण अभियन्ता, पौड़ी को प्रेषित। दिनांक 11/5/23 द्वारा आपत्ति में प्राप्त। आपत्तियों का निराकरण कर विस्तृत आगणन अधीक्षण अभियन्ता पौड़ी के पत्रांक-2171/630 याता-12/2023 दि0 27/3/24 द्वारा लम्बाई 5 कि0मी0 हेतु लागत रू0 271.36 लाख मात्र का मुख्य अभियन्ता, पौड़ी को प्रेषित। -- as on 06-Apr-2024

Rating : 66

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: