Work Profile Report [71W125]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-829/।।।-2/06 दि0 28/3/2006
TS Amount (lakhs) : 111.2 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
111.20
Resanction Cost :
277.11
Tentative Cost :
277.11
Exp. Upto Last Fy :
93.90
For CFY 2025-2026
Remaining :
183.21
Demand :
35.99
Allotment :
44.41
Exp in CFY :
1.18
Total Up to Date Exp :
95.08
Construction Started
Sanction on : 19 years 9 months ago
28 Mar 2006
Physical Progress:
At start of FY 2025-2026 :
60 %
Up to Date :
60 %
Tentative Completion date on : 1 year 2 months from now
31 Mar 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Excess requirement 165.91 has been counted as tentative cost increased from 111.2 to 277.11 .
पुनरीक्षित स्वीकृति के विरूद्ध अनुबन्ध गठन की कार्यवाही की जा रही है।
-- as on 18-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: