Work Profile Report [71W163]

fससबाड़ी-अमलेसा-लागबाड़ी-इलमोड़ा-ढयोडी धौलखेतखाल मोटर मार्ग का fनर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0-2555/।।।-(2)/06-41 (प्रा0आ0)/06 दि0 26/9/2006

TS Amount (lakhs) : 147.55 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

185.85

Resanction Cost :

185.85

Tentative Cost :

185.85

Exp. Upto Last Fy :

178.49

For CFY 2025-2026

Remaining :

7.36

Demand :

1.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

178.49

Work completed

Sanction on : 19 years 2 months ago

26 Sep 2006

Physical Progress:

At start of FY 2025-2026 :

100 %

Up to Date :

100 %

Tentative Completion date on : 1 year 3 months from now

17 Mar 2027

Actual Completion Date : 11 months 2 weeks ago

25 Dec 2024

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
10
10
10
-

Remark

view all

सहायक अभियन्ता के पत्रांक-51/19 सी0 दिनांक 6/3/23 द्वारा वन भूमि पत्रावली गठित कर प्रतिहस्ताक्षर हेतु प्रभागीय वनाधिकारी, का0टा0रि0प्रभाग, लैन्सडौन को प्रेषित। वन विभाग द्वारा प्रस्ताव अस्वीकृत कर दिया गया है। क्योंकि 1 कि0मी0 में मार्ग का निर्माण वन विभाग द्वारा करा दिया गया है। अतः यह कार्य निरस्त किया जाना है। -- as on 26-Dec-2023

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: