Work Profile Report [71W184]

Closed Work fदयोड़-धामधार मोटर मार्ग का fनर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0-2884/।।।-(2)/06-56(प्रा0आ0)/06 दि0 10/11/2006

TS Amount (lakhs) : 172.5 Lacs

Budget Financial Head : Not Available

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

172.50

Resanction Cost :

172.50

Tentative Cost :

172.50

Exp. Upto Last Fy :

170.86

For CFY 2025-2026

Remaining :

1.64

Demand :

0.00

Allotment :

1.64

Exp in CFY :

0.40

Total Up to Date Exp :

171.26

Work completed

Sanction on : 18 years 8 months ago

10 Nov 2006

Physical Progress:

At start of FY 2025-2026 :

75 %

Up to Date :

100 %

Tentative Completion date on : 1 year 1 month ago

31 May 2024

Actual Completion Date : 5 months 2 weeks ago

25 Jan 2025

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
10
8.5
8.5
-

Remark

view all

कार्य पूर्ण। -- as on 11-Apr-2025

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand