Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 8 | 0 |
71W262 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-4535/।।।(2)/11-72 (प्रा0आ0)/11 दि0 14/12/11
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
100.64
Resanction Cost :
100.64
Tentative Cost :
100.64
Exp. Upto Last Fy : 27.17
For CFY 2024-2025
Remaining : 73.47
Demand : 13.22
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 27.17
Construction Started
Physical Progress:
At start of FY 2024-2025 : 26 %
Up to Date : 26 %
Sanction on :
12 years 7 months ago
14 Dec 2011
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
fद्वतीय चरण की स्वीकृfत प्राप्त। -- as on 14-Jun-2021
Physical Peramenters