Work Profile Report [71W278]

जनपद पौड़ी गढ़वाल में राज्य योजना के अन्तर्गत भृगुखाल-बघेलगांव- जयहरी मल्ली- जयहरी तल्ली मोटर मार्ग का निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks

    Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : श्शा0सं0-6920/।।।(2)/11-134 (प्रा0आ0)/11 दि0 24/12/11

TS Amount (lakhs) : 63 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

63.00

Resanction Cost :

63.00

Tentative Cost :

63.00

Exp. Upto Last Fy :

3.01

For CFY 2025-2026

Remaining :

59.99

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

3.01

Construction Started

Sanction on : 14 years 1 week ago

24 Dec 2011

Physical Progress:

At start of FY 2025-2026 :

5 %

Up to Date :

5 %

Tentative Completion date on : 1 year 10 months from now

25 Nov 2027

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
5
5
5
-

Remark

view all

fद्वतीय चरण की स्वीकृfत प्राप्त। -- as on 31-Jul-2020

Rating : 5

No Forest Case in The Work

Hindrance / Bottleneck : Other Reason

Assets :

Work not linked with IM

Bridges on The Basis of AI: