Work Profile Report [71W386]

मा0मुख्यमंत्री जी की घोषणा सं0-464/2015 के अन्तर्गत यमकेश्वर से ढुंगा मोटर मार्ग का निर्माण कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks

    Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0 2724/।।।(2)/ 15-05(मु0मं0घो0)/2015 दिनांक 23.04.2015

TS Amount (lakhs) : 3.43 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

94.05

Resanction Cost :

94.05

Tentative Cost :

94.05

Exp. Upto Last Fy :

20.48

For CFY 2024-2025

Remaining :

73.57

Demand :

4.05

Allotment :

11.34

Exp in CFY :

11.75

Total Up to Date Exp :

32.23

Construction Started

Sanction on : 9 years 7 months ago

23 Apr 2015

Physical Progress:

At start of FY 2024-2025 :

18 %

Up to Date :

18 %

Tentative Completion date on : 3 weeks 5 days from now

20 Dec 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
5
5
0.000
5
0.000
0.000

Remark

view all

fद्वतीय चरण की स्वीकृfत प्राप्त। प्रfतकर प्रस्ताव गfठत fकया जा रहा है। -- as on 31-Jul-2020

Rating : 35

No Forest Case in The Work

No Hindrance / Bottleneck