Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.000 | 0.000 |
71W399 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-2221/।।।(2)/15-17 (प्रा0आ0)/2015 दि0 31/3/15
TS Amount (lakhs) : 85 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
85.00
Resanction Cost :
85.00
Tentative Cost :
85.00
Exp. Upto Last Fy : 6.43
For CFY 2024-2025
Remaining : 78.57
Demand : 1.95
Allotment : 1.95
Exp in CFY : 1.95
Total Up to Date Exp : 8.38
Construction Started
Physical Progress:
At start of FY 2024-2025 : 8 %
Up to Date : 8 %
Sanction on :
9 years 3 months ago
31 Mar 2015
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
शा0सं0-1621/।।।(2)/18-17 (प्रा0आ0)/2015 दिनांक 19/04/18 द्वारा द्वितीय चरण की स्वीकृति प्राप्त। -- as on 03-Feb-2023
Physical Peramenters