Work Profile Report [71W583]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-1075/।।।(2)/19-36(एम0एल0ए0)/2017 टी0सी0 ।। दि0 27/2/2019
TS Amount (lakhs) : 139.83 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
139.91
Resanction Cost :
139.91
Tentative Cost :
139.91
Exp. Upto Last Fy :
64.55
For CFY 2024-2025
Remaining :
75.36
Demand :
74.35
Allotment :
74.00
Exp in CFY :
15.45
Total Up to Date Exp :
80.00
Construction Started
Sanction on : 5 years 8 months ago
27 Feb 2019
Physical Progress:
At start of FY 2024-2025 :
28 %
Up to Date :
55 %
Tentative Completion date on : 4 months 1 day from now
25 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पहाड़ कटान कार्य पूर्ण । शेष कार्य प्रगति पर। -- as on 01-May-2024