Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.157 | 4.157 | 2.500 | 1.657 | 1.650 | 1.650 |
71W715 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0-3260/।।। (2)/ 21- 41 (एम0एल0ए0) /2017 दिनांक 2/9/2021
TS Amount (lakhs) : 175.72 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
175.72
Resanction Cost :
175.72
Tentative Cost :
175.72
Exp. Upto Last Fy : 107.34
For CFY 2024-2025
Remaining : 68.38
Demand : 60.00
Allotment : 2.00
Exp in CFY : 1.06
Total Up to Date Exp : 108.40
Work completed
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 100 %
Sanction on :
2 years 10 months ago
02 Sep 2021
Tentative Completion date:
2 months 2 weeks ago
30 Apr 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 01-May-2024
Physical Peramenters