Work Profile Report [71W733]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 5379/।।। (2)/ 21-41 (एम0एल0ए0)/ 2017टी0सी0आई0 दिनांक 11/11/2021
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
106.21
Resanction Cost :
106.21
Tentative Cost :
106.21
Exp. Upto Last Fy :
43.89
For CFY 2024-2025
Remaining :
62.32
Demand :
60.00
Allotment :
43.19
Exp in CFY :
14.13
Total Up to Date Exp :
58.02
Work completed
Sanction on : 3 years 1 week ago
11 Nov 2021
Physical Progress:
At start of FY 2024-2025 :
60 %
Up to Date :
100 %
Tentative Completion date on : 1 month 3 weeks ago
30 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष। -- as on 29-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: