Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.075 | 3.075 | 1.000 | 2.075 | 2.070 | 0.000 |
71W735 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0-5707(1)/।।। (2)/ 21-40 (एम0एल0ए0)/ 2017टी0सी0।। दिनांक 25/11/2021
TS Amount (lakhs) : 50.17 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
50.17
Resanction Cost :
50.17
Tentative Cost :
50.17
Exp. Upto Last Fy : 27.96
For CFY 2024-2025
Remaining : 22.21
Demand : 20.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 27.96
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
2 years 7 months ago
25 Nov 2021
Tentative Completion date:
5 months 2 weeks ago
31 Jan 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 14-Jan-2022
Physical Peramenters