Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 |
Closed Work 71W764 :
Administrative Approval Detail : 430(1)/।।।(2)/22-40 (एम0एल0ए0)/2017 टी0सी0-।।। दिनांक 6/1/2022
TS Amount (lakhs) : 190.52 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
190.52
Resanction Cost :
190.52
Tentative Cost :
190.52
Exp. Upto Last Fy : 189.82
For CFY 2024-2025
Remaining : 0.70
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 189.82
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
2 years 6 months ago
06 Jan 2022
Tentative Completion date:
10 months 2 weeks ago
31 Aug 2023
Actual Completion Date:
4 months 3 weeks ago
26 Feb 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। अवशेष देयकों के भुगतान की कार्यवाही की जा रही है। -- as on 07-Nov-2023