Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.33 | 1.33 | 0.000 | 1.33 | 1.330 | 0.000 |
71W841 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E letter No 44547 Dated 27/02/2023
TS Amount (lakhs) : 65.49 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
65.49
Resanction Cost :
65.49
Tentative Cost :
65.49
Exp. Upto Last Fy : 52.99
For CFY 2024-2025
Remaining : 12.50
Demand : 12.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 52.99
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
1 year 4 months ago
27 Feb 2023
Tentative Completion date:
3 months 3 weeks from now
14 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 26-Jun-2024
Physical Peramenters