Work Profile Report [71W873]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष, लोक निर्माण विभाग देहरादून के पत्रांक-895/07 याता- पी0एम0 जी0एस0वाई0-नि0 ।।। दिनांक 16/5/2023
TS Amount (lakhs) : 329.08 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
329.08
Resanction Cost :
329.08
Tentative Cost :
329.08
Exp. Upto Last Fy :
57.67
For CFY 2024-2025
Remaining :
271.41
Demand :
271.41
Allotment :
263.88
Exp in CFY :
263.88
Total Up to Date Exp :
321.55
Work completed
Sanction on : 1 year 7 months ago
16 May 2023
Physical Progress:
At start of FY 2024-2025 :
25 %
Up to Date :
100 %
Tentative Completion date on : 2 months 3 weeks ago
30 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष। -- as on 26-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: