Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.79 | 2.79 | 0.000 | 2.79 | 2.790 | 0.000 |
71W929 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 पत्रावली सं0-40068/45994 दिनांक 21/07/2023
TS Amount (lakhs) : 116.76 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
116.76
Resanction Cost :
116.76
Tentative Cost :
116.76
Exp. Upto Last Fy : 95.36
For CFY 2024-2025
Remaining : 21.40
Demand : 20.00
Allotment : 0.22
Exp in CFY : 0.22
Total Up to Date Exp : 95.58
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 100 %
Sanction on :
11 months 3 weeks ago
21 Jul 2023
Tentative Completion date:
1 month 1 week from now
31 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 29-Jun-2024
Physical Peramenters