Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.8 | 1.8 | 0.000 | 1.8 | 1.800 | 0.000 |
71W930 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 पत्रावली सं0-40068/45994 दिनांक 21/07/2023
TS Amount (lakhs) : 150.49 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
150.49
Resanction Cost :
150.49
Tentative Cost :
150.49
Exp. Upto Last Fy : 28.55
For CFY 2024-2025
Remaining : 121.94
Demand : 100.00
Allotment : 64.13
Exp in CFY : 64.13
Total Up to Date Exp : 92.68
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 85 %
Sanction on :
11 months 3 weeks ago
21 Jul 2023
Tentative Completion date:
1 week 5 days from now
30 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
1.50 कि0मी0 लम्बाई में इण्टर लाॅकिंग टाईल्स का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 27-Jun-2024
Physical Peramenters