Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 83 | 83 | 40.000 | 43 | 0.000 | 0.000 |
71W935 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2937/।।। (2)/23-01 (प्रा0आ0)/2019 दिनांक 11/8/2023
TS Amount (lakhs) : 455.58 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
455.58
Resanction Cost :
455.58
Tentative Cost :
455.58
Exp. Upto Last Fy : 392.23
For CFY 2024-2025
Remaining : 63.35
Demand : 63.35
Allotment : 50.00
Exp in CFY : 1.57
Total Up to Date Exp : 393.80
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 70 %
Sanction on :
11 months 6 days ago
11 Aug 2023
Tentative Completion date:
1 month 1 week from now
30 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
79 कि0मी0 में क्रैश बैरियर का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 01-Jun-2024
Physical Peramenters