Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 0.000 | 4 | 0.000 | 0.000 |
72W273 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1808/।।।(2)/16-38(एम0एल0ए0)/2016 दि0 26.05.2016
TS Amount (lakhs) : 203.84 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
203.84
Resanction Cost :
203.84
Tentative Cost :
203.84
Exp. Upto Last Fy : 156.09
For CFY 2024-2025
Remaining : 47.75
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.89
Total Up to Date Exp : 156.98
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
8 years 1 month ago
26 May 2016
Tentative Completion date:
8 months 1 week from now
30 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
उक्त मार्ग पी.एम.जी.एस.वाई. को हस्तान्तरित किया जा चुका है। मुआवजा वितरण का कार्य इस खण्ड द्वारा किया जाना है। अमीन की कमी के कारण कार्य बाधित है। -- as on 05-Nov-2023
Physical Peramenters