Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
72W318 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 508/।।।(2)/18-39 (एम0एल0ए0)/2017 दि0 09.02.2018
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
32.35
Resanction Cost :
32.35
Tentative Cost :
32.35
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 32.35
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
6 years 5 months ago
09 Feb 2018
Tentative Completion date:
1 year 8 months from now
30 Mar 2026
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 04: DFO
Bottelneck: no issue
वन भूमि प्रस्ताव उपप्रभागीय वनाधिकारी के पत्रांक 2760/12-1 दि0 28.01.2023 द्वारा आपत्तियों में प्राप्त। आपत्तियों का निराकरण करने की कार्यवाही की जा रही है इस कार्यालय के पत्रांक 666/14 सी0 दिनांक 11.05.2023 के द्वारा प्रभागीय वनाधिकारी पौड़ी को दूरी प्रमाण पत्र के सत्यापन हेतु पत्र लिखा गया। दूरी प्रमाण पत्र दि0 11.09.2023 को खण्ड में प्राप्त। प्रस्ताव दि0 15/05/2024 को सहायक अभियन्ता के पत्रांक 99/कैम्प द्वारा वनक्षेत्राधिकारी थलीसैंण को आपत्ति का निराकरण करने हेतु प्रेषित। इस कार्यालय के पत्रांक 947/14सी0 दि0 31.05.2024 के द्वारा प्रभागीय वनाधिकारी पौडी को आपत्तियों का निराकरण कर प्रतिहस्ताक्षरित करनें हेतु प्रेषित। -- as on 03-Jun-2024
Physical Peramenters