Work Profile Report [72W341]

जसपुरखाल मौटर मार्ग से ग्राम खराल से सोबरा तक सड़क निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : fजलाfधकारी गढ़वाल के पत्र संख्या 1323/fज0यो0/2018-19 fद0 26.01.2019

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

94.18

Resanction Cost :

94.18

Tentative Cost :

94.18

Exp. Upto Last Fy :

0.00

For CFY 2024-2025

Remaining :

94.18

Demand :

1.91

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.00

Alignment Approved

Sanction on : 5 years 10 months ago

26 Jan 2019

Physical Progress:

At start of FY 2024-2025 :

10 %

Up to Date :

10 %

Tentative Completion date on : 3 months 5 days from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
2
2
2
-

Remark

view all

मोटर मार्ग में ग्रामीणों द्वारा पूर्व स्वीकृत समरेखण में भूमि देने से इन्कार किया जा रहा है बहृउद्वेशीय शिविर दि0 17.10.2024 में प्राप्त निर्देशों के क्रम में पुराने प्रस्ताव को छोडते हुये नये समरेखण पर विचार करने हेतु निर्देशित किया गया है जिस हेतु इस कार्यालय के पत्रांक 1909/14सी0 दि0 23.10.2024 के द्वारा विवाद सुलझाने हेतु दि0 26.10.2024 को बैठक प्रस्तावित है। बैठक में अन्य समरेखण पर ग्रामवासियों द्वारा सहमति व्यक्त की गई है, जिसमें वनभूमि नही है। अतएव प्रकरण में वनभूमि प्रस्ताव की आवश्यकता नही है।

बैठक में अन्य समरेखण पर ग्रामवासियों द्वारा सहमति व्यक्त की गई है, जिसमें वनभूमि नही है। अतएव प्रकरण में वनभूमि प्रस्ताव की आवश्यकता नही है।
-- as on 05-Nov-2024

Rating : 11

Forest Case Pending At : 01: Withdraw

Hindrance / Bottleneck : Alignment Dispute

Assets :

Work not linked with IM

Bridges on The Basis of AI: