Work Profile Report [72W480]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0स0 कम्प्यूटरजनित क्रमांक 1/103710/2023 ई पत्रावली संख्या-38302 दि0 02.03.2023
TS Amount (lakhs) : 165.11 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
165.11
Resanction Cost :
165.11
Tentative Cost :
165.11
Exp. Upto Last Fy :
152.78
For CFY 2025-2026
Remaining :
12.33
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
152.78
In Maintenance After Completion
Sanction on : 2 years 3 months ago
03 Mar 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 7 months ago
28 Oct 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
4.800 किमी0 तक पहाड कटान का कार्य पूर्ण। -- as on 02-Dec-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: Jagatpuri Bridge