Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.1 | 2.1 | 2.100 | 0 | 0.000 | 0.000 |
72W485 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0स0 ई पत्रावली संख्या-41863 दि0 19.06.2023
TS Amount (lakhs) : 34.77 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
34.77
Resanction Cost :
34.77
Tentative Cost :
34.77
Exp. Upto Last Fy : 29.96
For CFY 2024-2025
Remaining : 4.81
Demand : 4.81
Allotment : 0.00
Exp in CFY : 2.56
Total Up to Date Exp : 32.52
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
1 year 4 weeks ago
19 Jun 2023
Tentative Completion date:
2 weeks 3 days ago
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध गठित । पहाड़ कटान का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 03-Apr-2024
Physical Peramenters