Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
72W493 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0स0 2451/111(2)/23-01 (प्रा0आ0)/2019 दि0 21.07.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
550.82
Resanction Cost :
550.82
Tentative Cost :
550.82
Exp. Upto Last Fy : 448.91
For CFY 2024-2025
Remaining : 101.91
Demand : 101.91
Allotment : 100.00
Exp in CFY : 37.88
Total Up to Date Exp : 486.79
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 95 %
Sanction on :
11 months 3 weeks ago
21 Jul 2023
Tentative Completion date:
1 week 6 hours ago
10 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध के सापेक्ष कार्य पूर्ण। अतिरिक्त मद एवं विचलन के सापेक्ष कार्य प्रगति पर। -- as on 02-Jul-2024
Physical Peramenters