Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 3.000 | 0.000 |
72W508 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0स0 ई पत्रावली संख्या-41863 दि0 08.09.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
237.17
Resanction Cost :
237.17
Tentative Cost :
237.17
Exp. Upto Last Fy : 30.17
For CFY 2024-2025
Remaining : 207.00
Demand : 207.00
Allotment : 50.00
Exp in CFY : 0.00
Total Up to Date Exp : 30.17
Construction Started
Physical Progress:
At start of FY 2024-2025 : 35 %
Up to Date : 35 %
Sanction on :
10 months 1 week ago
08 Sep 2023
Tentative Completion date:
8 months 1 week from now
30 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
जी0 1 एवं जी0 2 का कार्य प्रगति पर। -- as on 03-Apr-2024
Physical Peramenters