Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.9 | 1.9 | 0.000 | 1.9 | 1.900 | 0.000 |
72W509 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0स0 ई पत्रावली संख्या-27910 दि0 08.09.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
139.36
Resanction Cost :
139.36
Tentative Cost :
139.36
Exp. Upto Last Fy : 41.86
For CFY 2024-2025
Remaining : 97.50
Demand : 97.50
Allotment : 50.00
Exp in CFY : 21.64
Total Up to Date Exp : 63.50
Construction Started
Physical Progress:
At start of FY 2024-2025 : 35 %
Up to Date : 60 %
Sanction on :
10 months 1 week ago
08 Sep 2023
Tentative Completion date:
8 months 1 week from now
30 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
जी0 1, जी0 2 एवं जी0 3 का कार्य पूर्ण। 1.00 किमी0 लम्बाई में पी0सी0 का कार्य पूर्ण। -- as on 28-Jun-2024
Physical Peramenters