Work Profile Report [72W516]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : शा0स0 ई पत्रावली संख्या-36087 दि0 29.11.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
196.75
Resanction Cost :
196.75
Tentative Cost :
196.75
Exp. Upto Last Fy :
0.10
For CFY 2024-2025
Remaining :
196.65
Demand :
196.65
Allotment :
100.00
Exp in CFY :
31.63
Total Up to Date Exp :
31.74
Construction Started
Sanction on : 8 months 2 weeks ago
29 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
15 %
Up to Date :
20 %
Tentative Completion date on : 7 months 1 week from now
30 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अनुबन्ध गठित। अतिरिक्त पहाड कटान एवं स्कपर एवं जी01 का कार्य प्रगति पर। -- as on 28-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: