Work Profile Report [72W518]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : शा0स0 5082/III(2)2023-01(प्रा0आ0)/2023 दि0 09.11.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
658.44
Resanction Cost :
658.44
Tentative Cost :
658.44
Exp. Upto Last Fy :
283.74
For CFY 2024-2025
Remaining :
374.70
Demand :
374.70
Allotment :
370.35
Exp in CFY :
370.35
Total Up to Date Exp :
654.08
Construction Started
Sanction on : 1 year 1 month ago
09 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
50 %
Up to Date :
95 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 05-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: