Work Profile Report [72W529]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई0 पत्रावली संख्या- 25463 दिनांक 01.12.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
368.32
Resanction Cost :
368.32
Tentative Cost :
143.91
Saving
224.41
Exp. Upto Last Fy :
0.11
For CFY 2024-2025
Remaining :
368.21
Demand :
140.00
Allotment :
84.43
Exp in CFY :
84.43
Total Up to Date Exp :
84.53
Construction Started
Sanction on : 1 year 3 weeks ago
01 Dec 2023
Physical Progress:
At start of FY 2024-2025 :
15 %
Up to Date :
60 %
Tentative Completion date on : 3 months 4 days from now
30 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी03 तक का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 05-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: