Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.5 | 5.5 | 2.500 | 3 | 3.000 | 1.500 |
72W533 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 पत्रावली संख्या- 48456 दि0 15.01.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
71.56
Resanction Cost :
71.56
Tentative Cost :
71.56
Exp. Upto Last Fy : 24.99
For CFY 2024-2025
Remaining : 46.57
Demand : 46.57
Allotment : 30.00
Exp in CFY : 34.21
Total Up to Date Exp : 59.20
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 80 %
Sanction on :
6 months 2 days ago
15 Jan 2024
Tentative Completion date:
4 days 6 hours ago
13 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी0सी0 का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 05-Jun-2024
Physical Peramenters