Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 23.5 | 23.5 | 5.500 | 18 | 18.000 | 0.000 |
72W534 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 पत्रावली संख्या- 48456 दि0 15.01.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
339.76
Resanction Cost :
339.76
Tentative Cost :
339.76
Exp. Upto Last Fy : 24.92
For CFY 2024-2025
Remaining : 314.84
Demand : 314.85
Allotment : 100.00
Exp in CFY : 70.46
Total Up to Date Exp : 95.37
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 90 %
Sanction on :
6 months 2 days ago
15 Jan 2024
Tentative Completion date:
7 months 3 weeks from now
14 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी0सी0 का कार्य पूर्ण। शेष कार्य गतिमान है। -- as on 28-Jun-2024