Administrative Approval Detail : उत्तराखण्ड शासन, लोक निर्माण, अनुभाग-3 का पत्रांक- 868-।।।-3-2025/सी0आर0आई0एफ0/ई0- 69924 दि0 18.07.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : CRIF ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
5759.52
Resanction Cost :
5759.52
Tentative Cost :
5759.52
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
5,759.52
Demand :
2,300.00
Allotment :
2,300.00
Exp in CFY :
699.70
Total Up to Date Exp :
699.70
Construction Started
Sanction on : 6 months 5 days ago
18 Jul 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
21 %
Tentative Completion date on : 10 months 3 days from now
27 Nov 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अतिरिक्त पहाड कटान, दीवार निर्माण एवं कलवर्ट निर्माण का कार्य प्रगति पर। -- as on 20-Jan-2026