Work Profile Report [72W66]

जनपद पौडी गढ़वाल मे टेवलिया-रणियास (थलीसैंण- चैथान) मे मुख्य नदी पर पैदल सेतु का निर्माण 15 मी0
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0 171/111 (2)/08-42 (प्रा0आ0)/07 दि0 17-1-08

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : Bridges State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

0.10

Resanction Cost :

0.10

Tentative Cost :

0.10

Exp. Upto Last Fy :

0.09

For CFY 2025-2026

Remaining :

0.01

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.09

Work completed

Sanction on : 17 years 11 months ago

17 Jan 2008

Physical Progress:

At start of FY 2025-2026 :

10 %

Up to Date :

100 %

Tentative Completion date on : 9 months 2 days ago

31 Mar 2025

Actual Completion Date : 1 year 11 months ago

26 Jan 2024

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Bridge
1 (15m)
1 (15m)
1 (15m)
-

Remark

view all

जिस स्थान पर उक्त पैदल सेतु का निर्माण किया जाना था। वहा पर जिला पंचायत द्वारा पैदल सेतु का निर्माण किया जा चुका है। अतः कार्य को बन्द किये जाने की संस्तुति की जाती है। -- as on 02-Jan-2026

Rating : 90

No Forest Case in The Work

Hindrance / Bottleneck : Other Reason

Assets :

Work not linked with IM

Bridges on The Basis of AI: